Published by JaloPermit. Every number below comes from the state’s own rule, permit form, FAQ or DOT page, linked in the table, all checked November 18, 2026. This is a plain-English summary, not legal advice. States can change these lines, and the issued permit governs your move: the permit face wins.

A superload is an oversize or overweight load so big or heavy that the state takes it out of routine permitting and reviews it one by one. There is no single number. Each state draws its own line, and in most of the 16 states we checked it falls around 16 feet wide, 15 ft 6 in to 16 ft high, 150 to 160 feet long, or 160,000 to 200,000 pounds gross. Cross it and you can expect bridge or route analysis, extra paperwork, more lead time and sometimes police.

Below is what “superload” means in 16 states, each read today on the state’s own official source, plus where those sources disagree with each other. Some states use a different name (Wyoming says Class A, Texas says Super Heavy, Kansas splits it into superload and large structure), and a few print no fixed number at all.

A superload is almost always a nondivisible load first. If you are not sure your load qualifies as one, start with what is a nondivisible load. If you are not sure you need a permit at all, see do I need an oversize permit.

The short answer: where the superload line usually sits

Measure the truck with the load on it. In most states, crossing any one line is enough: width, height, length or gross weight. Here is how the 16 states in our table compare:

MeasureMost common superload line in the 16 states we checkedLowest we foundHighest we found
WidthOver 16 ft (Michigan, Minnesota, Missouri, Nebraska, New York, Pennsylvania, Tennessee)Over 15 ft, but only with 500,000 lb or more (Colorado)Over 20 ft for a Texas route inspection certification
HeightAbout 15 ft 6 in to 16 ftOver 15 ft (Michigan, Indiana)Over 18 ft 11 in for a Texas route inspection certification
LengthOver 150 ft (Michigan, Minnesota, Missouri, Nebraska)100 ft or more (Arkansas)Over 160 ft (New York, Pennsylvania)
Gross weightOver 160,000 lb (Missouri, Nebraska, Wyoming)Over 108,000 lb (Indiana State Police page)500,000 lb or more (Colorado)

Those are wide ranges. A 16 ft 6 in wide load is a superload in Michigan, Minnesota, Missouri, Nebraska, New York, Pennsylvania and Tennessee, but not by width alone in Arkansas (over 16 ft 6 in), Indiana (over 17 ft on its current fee sheet), Utah (over 17 ft) or Wyoming (over 18 ft). A 170,000 lb load is a superload in Missouri, Nebraska, Wyoming, Kansas and Tennessee, but not by weight in Minnesota (over 250,000 lb) or New York (200,000 lb). Plan each state on your route separately; see multi-state oversize permit trips.

Superload definitions in 16 states (checked Nov 18, 2026)

Each row was read today on the state’s own rule, permit form, FAQ or DOT page. “Over” means more than the number; “or more” means the number itself counts. Where a cell says not in the definition, that state’s source sets no line for that measure. Every state below has a state permit guide, linked in the first column. For other states, use the JaloPermit Atlas.

StateWidthHeightLengthGross weightNotesOfficial sourceChecked
Arkansas
State guide · Atlas
More than 16 ft 6 in15 ft 6 in or more100 ft or more overall180,000 lb or moreArkansas calls these “super loads of extraordinary weight or dimension” and issues them at ARDOT’s discretion.27 CAR § 111-110Nov 18, 2026
Colorado
State guide · Atlas
Over 15 ft (counts as two lanes), together with the weight testnot in the definitionnot in the definition500,000 lb or moreRule 609 also covers an empty expandable dual-lane trailer. CDOT’s permit page words it differently (see below). Applicants must send third-party proof of gross weight.2 CCR 601-4, Rules 300.10 and 609; CDOT truck permits pageNov 18, 2026
Indiana
State guide · Atlas
Over 17 ft (DOR fee sheet, State Police); over 16 ft (2017 DOR handbook)Over 15 ftOver 110 ftOver 200,000 lb (DOR fee sheet); over 108,000 lb (State Police); over 120,000 lb (2017 handbook)Three official Indiana sources print three different weight lines. See below.DOR permit fees sheet; ISP Superload Escorts page; DOR 2017 permitting handbookNov 18, 2026
Kansas
State guide · Atlas
Not a superload test. Over 16 ft 6 in is a “large structure”Not a superload test. Over 18 ft is a “large structure”not in the definitionOver 150,000 lb, or any axle group over the regulation limitsKansas splits big loads in two: superload (weight) and large structure (size). Superload and large structure permits are always reviewed by KDOT.K.A.R. 36-45-1 (KDOT copy); K-TRIPS user guideNov 18, 2026
Louisiana
State guide · Atlas
No single cutoff printedNo single cutoff printedNo single cutoff printedNo single cutoff; loads over 232,000 lb should be requested 4 to 6 weeks aheadDOTD’s 2026 regulations book has super-load application guidelines for overweight configurations. Loads over 900,000 lb may need an independent engineering firm’s analysis.DOTD 2026 rules and regulations bookNov 18, 2026
Michigan
State guide · Atlas
Over 16 ftOver 15 ftOver 150 ftnot in the definitionSingle trip permits are not issued above these limits. Superloads need a shipper’s letter and a certified route survey (Form 2465), at least 10 working days ahead.MDOT Form 2465; MDOT Form T-2Nov 18, 2026
Minnesota
State guide · Atlas
Over 16 ftOver 16 ftOver 150 ftOver 250,000 lbProcessing “can range from 5 business days to months.”MnDOT Guide to Transporting SuperloadsNov 18, 2026
Missouri
State guide · Atlas
Over 16 ftOver 16 ftOver 150 ft overallOver 160,000 lbAlso a superload: any axle over the maximum allowable weight, or a load not in a routine configuration. Every superload needs a route survey.MoDOT superload route survey sheetNov 18, 2026
Nebraska
State guide · Atlas
Over 16 ftOver 15 ft 11 inOver 150 ftOver 160,000 lbNondivisible loads only. The Lincoln Permit Office approves; the rule gives two different review times (see below).408 NAC 3-001.29 and 3-004.02; NDOT permit pricing sheetNov 18, 2026
New York
State guide · Atlas
Over 16 ftOver 15 ft 11 in (PERM 30); 16 ft or more (superloads page)Over 160 ftOver 200,000 lb (PERM 30); 200,000 lb or more (superloads page)Type 1S permit, filed with the Central Permit Office in Albany, with a manufacturer’s certification, a damage-responsibility letter, municipal letters and a bond.NYSDOT PERM 30; NYSDOT superloads pageNov 18, 2026
Pennsylvania
State guide · Atlas
Over 16 ftnot in the definitionOver 160 ftOver 201,000 lbNondivisible loads. Super load applications need Form M-936MDC and an M-936ARS route survey, and PennDOT lists a police escort on super loads. Any load over 14 ft 6 in high needs a route survey.PennDOT APRAS FAQNov 18, 2026
Tennessee
State guide · Atlas
Over 16 ftOver 15 ft 6 innot in the definitionOver 165,000 lbSuperloads move in daylight only. TDOT’s approximate processing time runs from 3 days (165,000 lb and under) to 30 days (over 500,000 lb).TDOT OS/OW permit FAQsNov 18, 2026
Texas
State guide · Atlas
Over 20 ft needs a route inspection certificationOver 18 ft 11 in needs a route inspection certificationOver 125 ft needs a route inspection certification“Super Heavy” permit when axle, axle group or gross weight exceeds TxDMV’s permit weight limitsTxDMV’s size and weight page does not use the word superload. Its heavy tier is called Super Heavy.TxDMV Texas size and weight limitsNov 18, 2026
Utah
State guide · Atlas
Over 17 ft goes to the superload teamOver 17 ft 6 in goes to the superload teamnot in the definitionOver 300,000 lb: weekday processing onlyLoads over 17 ft 6 in high, 17 ft wide or 300,000 lb are processed Monday to Friday, 8 a.m. to 5 p.m. Mountain, and approval may take up to 14 days.UDOT OS/OW provisions page; UDOT non-divisible load pageNov 18, 2026
Virginia
State guide · Atlas
No fixed number. Over the single trip limit of 15 ftNo fixed number. Over the single trip limit of 15 ftNo fixed number. Over the single trip limit of 150 ftNo fixed number. Over single trip axle and gross limitsA superload is a request that exceeds single trip limits and “requires research and analysis.” Submit at least 10 working days ahead. Over 18 ft wide, 250,000 lb, 200 ft long or 16 ft high, DMV may require a detailed travel plan.24VAC20-82-60; DMV 109Nov 18, 2026
Wyoming
State guide · Atlas
Over 18 ftOver 17 ftOver 120 ft overallOver 160,000 lb (or over Class B/C axle limits)Called a Class A permit (super load). Approved only by the Overweight Loads Office (OWL). Over 18 ft wide or 18 ft high needs at least 24 hours’ notice.WYDOT rules ch. 5, § 4Nov 18, 2026

We left out states we could not confirm today on an official source, including Illinois (its rule site would not load from our checker), California, Florida, Ohio and Oklahoma. Ohio’s rules, for example, print no single superload size cut-off; our Ohio guide explains what ODOT does instead. For those states, ask the permit office.

Where official sources disagree

This is where superloads trip people up. Sometimes two official sources from the same state print different lines:

  • Indiana: three weights. The Department of Revenue’s current permit fees sheet says a super load permit is for a load over 15 ft high, 17 ft wide, 110 ft long or 200,000 lb (DOR fees sheet). The Indiana State Police superload escort page uses the same size lines but “weight exceeding 108,000 pounds” (ISP). DOR’s older 2017 handbook says 16 ft wide and 120,000 lb (2017 handbook). Our Indiana guide covers Indiana’s sources in more detail. Follow the permit type DOR issues and ask Motor Carrier Services if your load sits between those numbers.
  • Colorado: “and” or “or”? Rule 609 makes a Super Load a combination of 500,000 lb or more that occupies two lanes (over 15 ft wide), or an empty expandable dual-lane trailer (2 CCR 601-4). CDOT’s permit page lists “Gross Vehicle Weight between exceeds 500,000 pounds, or has a double dolly and is greater than 15 feet wide” (CDOT). If your load is near either line, ask the Permit Office which permit it needs.
  • New York: at exactly the line. PERM 30 describes Type 1S as exceeding 15 ft 11 in high or 200,000 lb (PERM 30); NYSDOT’s superloads page says 16 ft high “or greater” and 200,000 lb “or greater” (superloads page). That only matters at exactly 200,000 lb, but it matters.
  • Nebraska: review time. The same rule says a superload review “may take up to ten business days” in its definition (001.29) and “up to five working days” in 004.02 (408 NAC 3). Plan for the longer one.

And states disagree with each other on what even counts:

  • Weight only. In Kansas, superload is a weight test (over 150,000 lb or over axle limits). Size goes to a separate “large structure” permit over 16 ft 6 in wide or 18 ft high (K.A.R. 36-45-1). Texas likewise uses Super Heavy for weight and a route inspection certification for size (TxDMV).
  • Size and weight together. Colorado’s rule needs both heavy weight and two-lane width.
  • No fixed number. Virginia defines a superload as a request over single trip limits that “requires research and analysis” (24VAC20-82-60). Louisiana’s regulations book has super-load application guidelines for overweight loads but prints no size line (DOTD rules book).
  • Missing measures. Pennsylvania’s definition has no height line, Tennessee’s has no length line, and Michigan’s has no weight line. Height still matters there: PennDOT wants a route survey for any load over 14 ft 6 in high.
  • “Over” vs “or more.” Arkansas counts 100 ft and 15 ft 6 in themselves (“or more”), and its length line is the shortest we found (27 CAR § 111-110). Most other states start just past the number.

What changes when your load becomes a superload

The permit still comes from the same state office, but the process gets heavier. In the sources we read today:

  • More lead time. At least 10 working days in Michigan (Form T-2) and Virginia (24VAC20-82-60); up to 14 days in Utah (UDOT); 3 to 30 days in Tennessee depending on weight (TDOT FAQs); 4 to 6 weeks in Louisiana over 232,000 lb (DOTD); and “5 business days to months” in Minnesota (MnDOT guide).
  • Route surveys. Missouri requires one for every superload: drive the route, measure lanes, shoulders, wires and signals, and file an emergency plan, with utility letters over 17 ft high (MoDOT). Michigan wants a certified route survey on Form 2465 (Form 2465), and Pennsylvania an M-936ARS (APRAS FAQ). Our guide to bridge clearance maps for trucks lists free official clearance sources.
  • Proof the load can’t be smaller. New York wants a manufacturer’s certification that the load cannot be broken down, a letter accepting responsibility for damage, letters from each municipality and a bond (PERM 30). Michigan wants a shipper’s letter explaining why the load cannot be reduced or moved by rail or water (Form 2465). Colorado wants third-party proof of gross weight, such as a certified scale ticket (Rule 609.2).
  • Bridge and engineering review. Virginia issues superloads only after a review or VDOT engineering analysis (24VAC20-82-60). Kansas superload and large structure permits are always reviewed by KDOT, and a superload without an existing bridge study cannot be ordered less than three days before the start date (K-TRIPS user guide). Axle weights get checked closely; see overweight permit axle weights.
  • Pilot cars, police and travel hours. Kansas requires at least one front and one rear pilot car (escort vehicle) on superloads (K.A.R. 36-45-8); PennDOT lists a police escort on super loads (APRAS FAQ); Tennessee superloads move in daylight only (TDOT FAQs). For pilot car counts by width, length and height, see how many pilot cars does my load need.

The permit face wins: call the issuing office

These definitions tell you when to expect the superload process. The state decides which permit it issues, and the permit you receive sets the route, dates, travel hours, pilot cars and any police escort for your move. If your dimensions sit near a line, or two official sources disagree, call the issuing permit office before you quote the job, not after.

Once the superload permit is issued, it is usually longer and more detailed than a routine permit. Our guide on how to read an oversize load permit walks through each part, and the OS/OW permit terms glossary explains the vocabulary. To see the route, pilot cars, curfews and dimensions on one card, drop the issued permit PDF into the JaloPermit decoder and check it against the original.

JaloPermit, which publishes this guide, is a reading aid for issued permit PDFs. It is not a permit-filing service and it does not plan routes or provide navigation. The issued permit always wins.

Questions about how JaloPermit reads a permit? Email support@jalopermit.org.

FAQs

What is a superload? A superload is an oversize or overweight load so large or heavy that the state takes it out of routine permitting and reviews it one by one, often with bridge or route analysis, extra paperwork and more lead time. Each state sets its own line. In most of the 16 states we checked it sits around 16 ft wide, 15 ft 6 in to 16 ft high, 150 to 160 ft long, or 160,000 to 200,000 lb gross.

What is considered a superload in Texas? TxDMV’s size and weight page does not use the word superload. It requires a route inspection certification on file for loads over 20 ft wide, 18 ft 11 in high or 125 ft long, and it sends loads whose axle, axle group or gross weight exceed its permit weight limits to a Super Heavy permit.

What is a superload in Missouri? MoDOT’s route survey sheet says a superload is a vehicle and load over 16 ft wide, 16 ft high, 150 ft overall length or 160,000 lb gross, or one over the maximum allowable axle weight or not in a routine configuration. Every Missouri superload needs a route survey.

Is a superload the same as an oversize load? No. Every superload is oversize or overweight, but most oversize loads are not superloads. A superload is the top tier, above what the state issues as a routine permit. A 12 ft wide load needs an oversize permit; in most states we checked it takes over 16 ft wide to become a superload.

How long does a superload permit take? Longer than a routine permit, and it depends on the state and the load. Michigan and Virginia ask for at least 10 working days, Utah says up to 14 days, Tennessee estimates 3 to 30 days by weight, Louisiana asks for 4 to 6 weeks over 232,000 lb, and Minnesota says anywhere from 5 business days to months.

Does a superload need a police escort? Sometimes. PennDOT lists a police escort on super loads, and other states add police by size or by the permit’s conditions. Pilot cars are a separate rule; see how many pilot cars your load needs. Your permit says what applies to your move.

Does JaloPermit get superload permits? No. JaloPermit is a reading aid, not a permit-filing service. Once a state issues your permit, upload the PDF and it decodes the route, pilot cars, curfews and dimensions onto one card. Guests get three free decodes a day with no account and no card. Logged-in users get 10 free decodes a day. After those free decodes, each one is $3.50. There is no subscription.